Travelodge Hotel - Clapham

  • Project Value: £4.9M
  • Contract Duration: 53 Weeks
  • Client: Sequoia Hotels

This scheme consisted of the construction of a 84 bed Travelodge Hotel with a ground floor retail space, including a three storey residential apartment block of six flats.

The hotel is constructed using a light weight steel frame system, prefabricated of site and lifted into position in panel sections. The bathrooms were also prefabricated off site.

The hotel opened in Summer 2012 and achieved BREEAM Very Good.