HM Young Offenders Institution, Portland.
- Project Value: £13M
- Contract Duration: 146 Weeks
- Client: Mansell Construction
- Services Consultant: Troup Bywater Anders
This was a refurbishment of HM Prison Service project spread over three phases of an live operating young offenders Institution.
All services where replaced as part of the contract this included lighting, power, security, fire alarms, prison call system, heating, ventilation and Public health.
The main boiler plantroom was completely refurbished and new plant installed. Temporary boiler plant was installed to serve the existing prison while the works progressed.